Renovation Week the Last: Double Bar

All inspections passed.

Building permit taken down from the window.

Contractor doing final touchups.

(Previously)

How long?

1__python

225 days.

How do we like it?

It’s pretty awesome.

Are there things we wish we had done differently?

How long do you have?

Will we ever do this again?

Ask me in a year. Or 10.

Hey, did they ever grout that tile?

Yep.

img_3534

Renovation Week 24: Now Sit Right Back

We must be getting close to the end one way or the other; our contractors have started taking away tools that they’ve been storing in my garage for months. That has to mean something.

When last we spoke, the critical path for this project went directly through the island cabinets that were being built. Without them, the countertop people won’t finish their templates. Without the countertops we can’t install sinks and final plumbing, or do the tile backsplash. Without the island, the Minnow would be lost.

Continue reading “Renovation Week 24: Now Sit Right Back”